The Wankulukuku-Mutundwe Pipe Laying Project is underway and making steady progress. The contractor recently received 50 pieces of DN250, with an additional 52 pieces expected to arrive tomorrow.
The team has already trenched 1500 out of 2000 meters, and the pipe laying for the pieces received is ongoing. Pipe laying is expected to be completed by the end of the week.
In addition, the Kabusu-Kitemu project is ongoing, with the network team installing provisions for interconnections at the connection point in Kabusu.