After a successful community and stakeholder engagement was carried out on 25th August 2022, Ibanda Area’s Technical team resumed works to ensure water stabilization in the Area. The team expects to complete laying the 8″ steel pipe section on 26th August 2022.
The Area is also expecting to receive 6″ steel pipes from Central store to complete laying pipes in the remaining sections within the swamps.
Much appreciation goes to the corporation’s Managing Director and his top management for the support as the Area remains committed to Water for All.